Project Report for September 2024
- Report Date
- September 2024
Achievements this period
- O1 - Successfully deployed updating EUCLID & Eugex Reads and BI Universes to read from MCI tables
- O2 - All large data tables that do not require further analysis or agreement deleted
Issues
- (New) O1 - Delayed deployment on the day of release due to conflicting priorities of team members. This will be added to Lessons Learned log
Next Steps
- O1 - Switch off updates that write data to STU tables
- O2 - Agreement across schools of data retention periods to be obtained
- O2 - Begin writing deletion code
Key Milestones
| Stage | Milestone | Due Date | Previous Date | Complete | |
|---|---|---|---|---|---|
| Analyse | O2 Data retention policy agreed with users | 04-Oct-2024 | 30-Aug-2024 | No | |
| Build | O1 STU updates switched off | 18-Oct-2024 | 27-Sep-2024 | No | |
| Build | O2 Data retention policy built | 31-Oct-2024 | 27-Sep-2024 | No | |
| Build | O2 Data retention policy tested | 15-Nov-2024 | 01-Nov-2024 | No | |
| Build | O2 Data retention policy trained | 29-Nov-2024 | No date available | No | |
| Deliver | Delivery of Project Outcomes (MAJOR MILESTONE) | 31-Jan-2025 | 23-Sep-2024 | No | |
| Deliver | O2 Data retention policy LIVE | 31-Jan-2025 | No date available | No | |
| Close | Project Closure (MAJOR MILESTONE) | 25-Apr-2025 | 08-Nov-2024 | No |
- Approved budget
- 204.0 days
- Activity this month
- 35.6 days
- Activity this year
- 63.2 days
- Activity to date
- 166.1 days
- Estimate to complete current year
- 46.7 days
- Estimate to complete future years
- 0.0 days