Project Report for November 2024

Report Date
November 2024

Achievements this period

  • O1 - No negative feedback received since deployment
  • O2 - Retention policies and periods agreed with colleges and schools
  • O2 - Deletion processes tested - one outstanding

Issues

  • (NEW) O2 - One of the deletion processes failed in testing and therefore required some rework that has now been completed. Will be tested w/c 2 Dec (RESOLVED)
  • (NEW) Overall - project is slightly over budget and is suspected to exceed tolerance therefore a budget change request has been submitted

Next Steps

  • O2 - Deletion processes released to TRN
  • O2 - Deletion processes UAT to take place w/c 9 Dec by Operations team
  • Budget change request to be noted at Apps Review on Thurs 5 Dec

Key Milestones

Stage Milestone Due Date Previous Date Complete  
Build O2 Data retention policy tested 29-Nov-2024 15-Nov-2024 No

view

Build O2 Data retention policy UAT signed off in TRN environment 20-Dec-2024 29-Nov-2024 No

view

Deliver O2 Data retention policy LIVE 31-Jan-2025 No date available No

view

Deliver Delivery of Project Outcomes (MAJOR MILESTONE) 31-Jan-2025 23-Sep-2024 No

view

Build O1 STU updates switched off 31-Jan-2025 18-Oct-2024 No

view

Deliver O2 Large data tables deletion sucessfully handed over to Operations 28-Feb-2025 No date available No

view

Deliver O2 Operations successfully run first large data table deletion exercise 28-Mar-2025 No date available No

view

Close Project Closure (MAJOR MILESTONE) 25-Apr-2025 08-Nov-2024 No

view

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
RAG Commentary
Cost - (NEW) Overall - project is slightly over budget and is suspected to exceed tolerance therefore a budget change request has been submitted
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Programme Manager
Activity
Approved budget
204.0 days
Activity this month
21.0 days
Activity this year
107.4 days
Activity to date
210.3 days
Estimate to complete current year
10.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Euclid Technical Legacy - Other
Code
SAC102
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Jack Ross
Project Sponsor
Lizzie Beattie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Apr-2024
Planning Date
31-May-2024
Delivery Date
28-Feb-2025
Close Date
31-Jul-2025
Overall Priority
Normal
Category
Compliance