Report for June 2025

Report Date
June 2025

 

Achievements in Last Period

  • One release achieved this month:  New report released for Extensions balance to the EC Service - allows EC service to now check the balance of extensions remaining for students without having to manually run through each case.

  • Achievements - The underlying database has been upgraded to the latest version which should provide performance improvements. Relevant information on evidence for students

  • Resits Extensions: Development completed and passed in TRN, awaiting confirmation from EC Service ahead of release to LIVE

  • Bulk confirming EC outcomes in APT:  Review in CSI Project, Dev to be started this month

  • Automatic closing of Extensions applications: Current in TEST

  • Extensions Dashboard: Dashboard showing extensions balances for students to be tested by Student Advisors

  • Long-term fixes for EC cases with no statements has been prioritized to reduce fixes in the live database. 

Issues 

  • (resolved) Scope confirmed at end April
  • (new) Lead BA moving as new role - mitigation in terms of support till end July
  • (new) Lead Developer on Jury Duty

Next Steps​

  • Planning next releases
  • Build and testing the next changes to functionalities 
  • Complete Closure Report and Close Project

Next milestones (revised)

 

Build Build - Improve student and staff dashboards usability, notify students, ESC team and student advisors about case statuses and when evidence is added (O3) 21-Apr-2025
Deliver Improve student and staff dashboards usability, notify students, ESC team and student advisors about case statuses and when evidence is added (O3) 02-May-2025
Deliver Solution for providing extensions on resits in time for next summer resit 30-May-2025
Deliver Deployment Sign off Review - incl Doc and handover 31-Jul-2025
Deliver On going support of the Live service across peak periods (new) 31-Jul-2025
Close Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Adapting ESC (Extensions and Special Circumstances) to support policy changes
Code
SAC105
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lisa Dawson
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
15-Jan-2024
Planning Date
19-Apr-2024
Delivery Date
17-Oct-2025
Close Date
24-Oct-2025
Programme Priority
2
Overall Priority
Higher
Category
Discretionary

Documentation