Report for August 2025

Report Date
August 2025

Achievements in Last Period

  • Release 18, which delivered functionality in order to deliver auto closure scripts was successfully deployed to Live 20-Aug-2025

  • New Project Manager assigned to the Project

  • All remaining Must Have Jira have been estimated to understand what is required to complete them. 

  • Sprint 27 was completed and sprint 28 has been started.

 

Issues 

 

Next Steps​

  • Project SAC105 is currently under review, it will need to be confirmed between Defeng Ma and Lesley Teague-McHugh (on Lesley’s return from annual leave – post 01-Sep-2025) how long the current Project can potentially be extended out, it is understood that discussion will take place to take the Project beyond the Change Freeze, that ends 29 September 2025, in order to give time to deliver and deploy the remaining Must Have Jira (TBC). Once established / agreed the remaining Project deliverables need to be reviewed, the Project then needs to be re-planned with the milestones updated accordingly
  • Finish development of and plan the remaining release / releases post Change Freeze (29-Sep-2025 - TBC)
  • Draft a Closure report and agree Project closure date

 

Future Milestones

#Please note that all of the milestones below are being reviewed and will need to be re-established and agreed as part of re-planning (as per Next Steps):

Stage Milestone Due Date
Build Build - Improve student and staff dashboards usability, notify students, ESC team and student advisors about case statuses and when evidence is added (O3) 21-Apr-2025
Deliver Improve student and staff dashboards usability, notify students, ESC team and student advisors about case statuses and when evidence is added (O3) 07-Apr-2025
Deliver Solution for providing extensions on resits in time for next summer resit 30-May-2025
Deliver On going support of the Live service across peak periods (new) 31-Jul-2025
Deliver Deployment Sign off Review - incl Doc and handover 31-Jul-2025
Close Close 15-Aug-2025

 

 

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Issue - Project is under review / re-planning based on still have a number of Must Have stories to deliver and needing to deploy any updates (notably filters) after the September Change Freeze. Impact - Budget and milestones, notably Delivery & Closure dates are now out of tolerance and need updating Mitigation - Complete planning to take Project to Closure and review with SSP Stakeholders / USG Programme Manager and update milestones through Change at Apps Review
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
745.0 days
Activity this month
48.4 days
Activity this year
48.4 days
Activity to date
1083.7 days
Estimate to complete current year
9.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Adapting ESC (Extensions and Special Circumstances) to support policy changes
Code
SAC105
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lisa Dawson
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
15-Jan-2024
Planning Date
19-Apr-2024
Delivery Date
17-Oct-2025
Close Date
24-Oct-2025
Programme Priority
2
Overall Priority
Higher
Category
Discretionary

Documentation