April 2025

Report Date
April 2025

Achievements

  • Project brief reviewed
  • Work continues on understanding the issues of the current system and student user needs.  The first student workshop has taken place and a further is scheduled to consider design elements of an initial prototype produced by our AI Interns
  • Reviewing the results of the Course Enrolment CI group survey for PATH impacts

  • Secured resources with Python knowledge from IS Dev Services to support the design 

Issues

  • n/a

Next steps

  • Continue engagement with users to articulate new requirements
  • Technical design: the new requirements will inform the HL architecture required and the technical specs to build the Dev environment
  • Complete handover to new PM

 

Next milestones:

 

Analysis - High Level requirements validated - survey 

6 Jun 25 

Path Technical Design Review 

30 Jun 25 

Set up Dev environment 

24 Jul 25 

MVP (Objective 1) -Checkpoint: Plan work packages, High Level estimate and resources 

31 Jul 25 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Path rewrite & enhancements
Code
SAC110
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Lizzie Beattie
Current Stage
Execute
Status
Suspended
Project Classification
Grow
Start Date
03-Feb-2025
Planning Date
06-May-2025
Delivery Date
31-Jul-2026
Close Date
01-Oct-2026
Overall Priority
Normal
Category
Compliance

Documentation