Report for June 2025
- Report Date
- June 2025
Achievements
- Confirmed no SAIM resource available until after August 25
- Met with Sponsor to discuss way forward with no SSP Involvement - ISG only approach agreed.
Issues
(new) approval to start the project but resources not confirmed Initiation delay
Next steps
- Revise PID to suit new project scope
- Pass case for suspension back to ISG re: funding
Next milestone:
- TBC
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days