Report for August 2025

Report Date
August 2025

 

Achievements

  • Confirmed no SAIM resource available
  • Confirmed SSP BA resources are currently not available due to L&T workstream priorities
  • Some analysis is underway with ISG resources 

Issues

  • Approval to start the project has not been agreed due to resource conflicts with the learning and teaching workstream
  • Registry resources are likely to be required for 6-12 months to undertake the analysis

Next steps

  • Agree funding for continuing the project with the required resources from registry
  • Escalation to agree on how this work will be prioritised alongside L&T workstream

Next milestone:

  • TBC
Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
RAG Commentary
Overall RAG status is now RED due to the following: Issue: There has been a delay in securing registry resources to support the project due to conflicting demands by the learning & teaching workstream. Impact: There will be a delay in delivering any outcome that would support a financial benefit in reducing operating costs. Next Steps: This now requires escalation so that prioritisation decisions can be made to allow the project to continue.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BI Suite/EUCLID reporting Discovery
Code
SAC112
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Lesley Teague-McHugh
Project Sponsor
Alex Carter
Current Stage
Initiate
Status
Not Started
Start Date
15-May-2025
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
Category
Discretionary

Documentation