Report to 23-Jan 2018
- Report Date
- January 2018
Phase 1
- TEST has been cleared down and refreshed ready for next round of UAT testing
- New 'NEP Update' and 'Exam Selector' workflows have been promoted from DEV to TEST
- Tier4 data mapping issue fixed in test , 551 missing students added to Exam Scheduler
- Re-plan and new budget agreed with SEP Programme Sponsor and Project Sponsor at meeting on 18th-Dec
- New Go-Live date of 10-June 2018 agreed to enable new solution to go live for Aug 2018 resits exam diet
- 'Exam Selector' workflow has been delivered to DEV for unit testing by UoE
-
Calsync config completed in TEST - some issues to escalate to S2Unified and IS S/W Dev team
--
Phase 2
- Budget for new Phase 2 agreed - 100d for ISG effort , and equivalent from Business and usual teams / SEP to support longer duration of project. Project extended by 6 months
- Phase 2 - resource bookings for IS ADO S/W Dev team agreed ( Thalia NikoLaidou assigned in Feb and Mar 2018) - Thalia unavailable 3d during w/c5-Feb and w/c 12-Feb due to resource conflict with UWP006 project
--
Issues
-
Open - Error re-loading invigiliator data - Dev Tech investigating - ? table dropped in EUGEX as part of EUCLID TEST upgrade
-
Open - Scientia have replicated the application crashes experienced by UoE exams team in ES v3.5.8 – Scientia support team raising the issue with the ES product manager
- Open - Critical bug with Exam Scheduler with error in calculation of extra reading time when exam duration changes - reported to Scientia support on 8-Jan - awaiting response
- open - EQIA not completed - task escalated to Scott Rosie
- Resolved - Inadequate Exam business team resources to support extended Phase 1 and new Phase 2 ( owner Scott Rosie) - back-fill now in place until May 2018
--
Risks
- Resource conflicts within SSP / Student systems delay Phase 1 acceptance sign-off - Student systems input is critical to resolve errors with WP2 incoming data feed (Owner Kirsty Roseweir)
- Legacy systems could fail before being replaced
- Scientia technology constrains final end-to-end solution
Next Steps
-
Agree and send Comms to explain new delivery plan for SAS005 to SEP board , Exam Operations groups and other stakeholder
- Phase 1 and Phase 2 - update dates for future milestones , build new plan in ASTA and request resources to end of Phase 2
- Phase 1 - complete testing of exam scheduling for NEP and non-NEP students ( in progress in TEST) by end of Feb 2018
- Phase 1 - Complete build work for new BI Suite universe by end of Feb 2018
- Phase 1 - Complete build work for outgoing feed to Calsync by end of Feb 2018
- Phase 1 - Complete build work on replacement Web Exam Timetables by end of Feb 2018
- Phase 2 - Start business analysis and schedule user workshop with cross-section of users from schools
- Approved budget
- 470.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 240.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days