Report to 23-Jan 2018

Report Date
January 2018

Phase 1

  • TEST has been cleared down and refreshed ready for next round of UAT testing
  • New 'NEP Update' and 'Exam Selector' workflows have been promoted from DEV to TEST
  • Tier4 data mapping issue fixed in test , 551 missing students added to Exam Scheduler
  •  
  • Re-plan and new budget agreed with SEP Programme Sponsor and Project Sponsor at meeting on 18th-Dec
  • New Go-Live date of 10-June 2018 agreed to enable new solution to go live for Aug 2018 resits exam diet
  • 'Exam Selector' workflow has been delivered to DEV  for unit testing by UoE
  •  Calsync config completed in TEST - some issues to escalate to S2Unified and IS S/W Dev team

--

Phase 2

  • Budget for new Phase 2 agreed - 100d for ISG effort , and equivalent from Business and usual teams / SEP to support longer duration of project. Project extended by 6 months
  • Phase 2 -  resource bookings for IS ADO S/W Dev team agreed ( Thalia NikoLaidou assigned in Feb and Mar 2018) - Thalia unavailable 3d during w/c5-Feb and w/c 12-Feb due to resource conflict with UWP006 project

--

 

Issues

  • Open - Error re-loading invigiliator data - Dev Tech investigating - ? table dropped in EUGEX as part of EUCLID TEST upgrade

  • Open - Scientia have replicated the application crashes experienced by UoE exams team in ES v3.5.8 – Scientia support team raising the issue with the ES product manager

  • Open - Critical bug with Exam Scheduler with error in calculation of extra reading time when exam duration changes - reported to Scientia support  on 8-Jan - awaiting response
  • open - EQIA not completed - task escalated to Scott Rosie
  • Resolved - Inadequate Exam business team resources to support extended Phase 1 and new Phase 2 ( owner Scott Rosie) - back-fill now in place until May 2018 

 

--

Risks

 

  • Resource conflicts within SSP / Student systems delay Phase 1 acceptance sign-off - Student systems input is critical to resolve errors with WP2 incoming data feed (Owner Kirsty Roseweir)
  • Legacy systems could fail before being replaced 
  • Scientia technology constrains final end-to-end solution

 

Next Steps

 

  • Agree and send Comms  to explain new delivery plan for SAS005 to SEP board , Exam Operations groups and other stakeholder

  • Phase 1 and Phase 2 - update dates for future milestones , build new plan in ASTA and request resources to end of Phase 2
  • Phase 1 - complete testing of exam scheduling for NEP and non-NEP students ( in progress in TEST) by end of Feb 2018
  • Phase 1 - Complete build work for new BI Suite universe by end of Feb 2018
  • Phase 1 - Complete build work for outgoing feed to Calsync by end of Feb 2018
  • Phase 1 - Complete build work on replacement Web Exam Timetables by end of Feb 2018
  • Phase 2 - Start business analysis and schedule user workshop with cross-section of users from schools
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
AMBER - Issue - Resource conflict - BA supporting Phase 1 testing and also need to start analysis for Phase 2 , ahead of start of Phase 2 design work in Feb 2018
Change Status
Activity
Approved budget
470.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
240.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days