Report to 20-Feb 2018

Report Date
February 2018

Summary RAG for each Work package

 

Work package RAG summary
ID Description RAG Status Comments    
Phase 1 End-to-End process for Main exam diets RED      
WP1 Exam Scheduler product RED New issue with global setting for the scheduling constraint on 'Mixed Duration activities' - team are investigating workaround of toggling the parameter between scheduling main and special sittings    
WP2 Student Systems Connector AMBER solutions for open issues agreed while Scientia consultants on-site on 6,7,8-Feb incl new host key for Exam requirement    
WP3 Calsync Exam feed to Office365 AMBER Config done in TEST, open issues - data type mismatch - Stephen Smith working with supplier S2Unifed    
WP4A BI Suite Reporting GREEN Testing of new BI Suite universe and initial reports done, small amount of rework identified for S/W dev team    
WP4B Generic Web Timetables GREEN Built and tested. Working OK.    
           
Phase 2 Exceptions for Resits and Fixed date exam resits GREEN      
WP5 Resits GREEN analysis started - more data on resits available direct from EUCLID than expected ( APT )    
WP6 Fixed date exam resits GREEN analysis started    
WP7 Calsync Enhancements ( from Calsync lessons learned ) GREEN

critical issues are being resolved by supplier S2unified and managed by IS Service Management as part of the business-as-usual service.

 

   
           

 

Phase 1

  • James Slattery not called for Jury duty so available to continue full data prep and scheduling  dry run in TEST 
  • Alison Ramsay unavailable w/c 12-Feb while focusing on business-as-usual exam scheduling for May 2018 exam diet

--

Phase 2

  • More resit data available direct from EUCLID and could be presented to Exam Scheduler in the EUGEX view
  • IS S/W dev team developer (Thalia)  not available to start design work due to other project work for UWP006
  • More analysis and school workshops to be completed by Andy Crossland and Sabrina Fijalkowski before Thalia can start design work

--

 

Issues

  • Change to Benefits in PID - the identified £15k of staff cost savings within Exam Timetabling team won't be realised - volume of workarounds in new system too high

  • New Open - Scientia Exam Scheduler product - scheduling constraints ( system parameters) are set globally , and can't be set differently for Main exam sittings and Special exam sittings

  • Open - Scientia have replicated the application crashes experienced by UoE exams team in ES v3.5.8 – Scientia support team raising the issue with the ES product manager

  • Open - Critical bug with Exam Scheduler with error in calculation of extra reading time when exam duration changes - reported to Scientia support  on 8-Jan - awaiting response
  • open - EQIA not completed - task escalated to Scott Rosie
  • Resolved - Inadequate Exam business team resources to support extended Phase 1 and new Phase 2 ( owner Scott Rosie) - back-fill now in place until May 2018 

 

--

Risks

 

  • Availablity of Scientia technical resource will delay Phase 1 acceptance sign-off - as Scientia need to do some work on the Student Systems Connector before UoE team can retest
  • Resource conflicts within SSP / Student systems could delay Phase 2 analysis  (Owner Kirsty Roseweir)
  • Legacy systems could fail before being replaced 
  • Scientia technology could constrain final end-to-end solution - more workarounds than envisaged in PID - smaller cost savings of staff time in Exam timetabling team

 

Next Steps

 

  • Phase 1 - WP1 and WP2 - Agree workarounds with Scientia and the UoE Exams team , and take some benchmark timings to compare against the legacy system
  • Phase 1 - WP1 and WP2 - complete testing of exam scheduling for NEP and non-NEP students ( in progress in TEST) by end of Feb 2018
  • Phase 1 - WP3 - Start integration testing from Mon 5-March
  • Phase 1 - WP4 - Complete BI Suite rework from UAT testing
  • Phase 2 - Complete business analysis and get input from schools via a workshop with school stakeholders
  • Phase 2 - Start design work, after business requirements agreed
Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
GREEN
Overall
RED
RAG Commentary
Issue - Global setting for constraint on 'mixed duration activities' does not fit UoE business processes for scheduling special exam sittings - onerous workaround will be required - will reduce benefits realised
Change Status
Activity
Approved budget
470.0 days
Activity this month
0.0 days
Activity this year
230.0 days
Activity to date
260.0 days
Estimate to complete current year
190.0 days
Estimate to complete future years
20.0 days