Report to 29-May 2018

Report Date
May 2018

Summary RAG for each Work package

Go Cab approval sought on Tues 15-May , ahead of deployments to  LIVE.

Deployments to LIVE in progress.

Some on-going testing and re-work for BI Suite reporting and Calsync.

--

Deadline for Calsync changes by 1st June

Deadline for Reporting changes by 11th June 

--

Phase 3 added to scope and budget split between 17-18 and 18-19 agreed with programme owner (budget holder) 

Work package RAG summary
ID Description RAG Status Comments    
Phase 1 End-to-End process for Main exam diets GREEN      
WP1 Exam Scheduler product GREEN Deployed to LIVE with copy of Reference data - Manual workarounds available for all known issues    
WP2 Student Systems Connector GREEN

final checks in pre-LIVE env - in progress

   
WP3 Calsync Exam feed to Office365 AMBER

 final UAT in progress in TEST - to complete by Fri 1st June

   
WP4A BI Suite Reporting AMBER

new re-work identified - a mix of universe changes and report changes required - in progress with  IS S/W Dev team and IS Service management - to complete by 11th June

   
WP4B Generic Web Timetables GREEN

On Track. Deployment to LIVE in progress

   
           
Phase 2 Exceptions for Resits and Fixed date exam resits GREEN      
WP5 Resits GREEN On Track - EUGEX changes deployed to LIVE    
WP6 Fixed date exam resits AMBER some more testing to be done     
WP7 Calsync Enhancements ( from Calsync lessons learned for Teaching Timetable ) GREEN

On Track - The Critical issues with deletions has been resolved by  hotfix from supplier S2unified and is being managed by IS Service Management as part of the business-as-usual service.

 

   
           
Phase 3 Upgrade to ESv3.5.9 and small enhancements Not started      
WP8 Upgrade to ES v3.5.9 Not started      
WP9 Small enhancements / bug fixes for Dec 2018 main exam diet Not started      

 

 

 

 

 

 

 

 

 

 

 

 

Issues

 

  • Open - new re-work identified for BI Suite Universe and Reports -in progress with  IS S/W Dev team and IS Service management
  • Open -  Scientia expect ES v3.5.9 will be released during June 2018  - not critical for Aug resits - must be applied to LIVE by Sept 2018 for Dec 2018 main exam diet

 

Risks

 

  • Legacy systems could fail before being replaced (low) 
  • Scientia technology has already and will constrain final end-to-end solution - more workarounds required than envisaged in business case - impact : additional staff costs in Exam timetabling team

 

Next Steps

 

  • Phase 1 - WP3 - Calsync -  complete testing by 1st June - testing looking OK to date
  • Phase 1 - WP4 - Complete BI Suite / Web exam timetables rework by 11th June
  • Phase 1 and Phase 2 - complete implementation plan for deploy to LIVE w/c  11th June
  • Business exams team start to use new solultion on Mon 25th June
  • Post go-live scheduling support from Scientia business consultant on 4/5/6-July 2018
  • Publish Aug resits exam timetable w/c 23--July 2018 - first use of the Calsync / Office365 feed

 

Milestones

 

see Milestone log

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue - new re-work on BI Suite reporting identified - to be fixed by 25th June
Change Status
Activity
Approved budget
470.0 days
Activity this month
20.0 days
Activity this year
285.0 days
Activity to date
369.0 days
Estimate to complete current year
68.0 days
Estimate to complete future years
52.0 days