Report to 12-June 2018
- Report Date
- June 2018
Summary RAG for each Work package
Final deployments to LIVE done for all components, except for BI Suite Universe and Calsync
Some on-going testing and re-work for BI Suite reporting still in progress.
--
On target for first use by Exam timetabling business team from Mon 25-June
--
Phase 3 added to scope, and the new budget split between 17-18 and 18-19 agreed with programme owner (budget holder)
ID | Description | RAG Status | Comments | ||
---|---|---|---|---|---|
Phase 1 | End-to-End process for Main exam diets | GREEN | |||
WP1 | Exam Scheduler product | GREEN | Deployed to LIVE with copy of Reference data - Manual workarounds available for all known issues | ||
WP2 | Student Systems Connector | GREEN |
Deployed to LIVE - passed final checks in pre-LIVE env |
||
WP3 | Calsync Exam feed to Office365 | GREEN |
UAT done, some final checks in pre-Live advisable before 20-June cleardown , and Go-Live on 25-June, Calsync for Exams won't be switched-on until w/c 23-July 2018 |
||
WP4A | BI Suite Reporting | AMBER |
BI Suite in TEST - second round of Universe re-work build and Report re-work build done, back to business users for another round of Testing, enough of the basic reports available for initial go-live SSRS in TEST |
||
WP4B | Generic Web Timetables | GREEN |
Deployment to LIVE complete |
||
Phase 2 | Exceptions for Resits and Fixed date exam resits | GREEN | |||
WP5 | Resits | GREEN | On Track - EUGEX changes deployed to LIVE | ||
WP6 | Fixed date exam resits | GREEN | some more testing to be done | ||
WP7 | Calsync Enhancements ( from Calsync lessons learned for Teaching Timetable ) | GREEN |
On Track - The Critical issues with deletions has been resolved by hotfix from supplier S2unified and is being managed by IS Service Management as part of the business-as-usual service.
|
||
Phase 3 | Upgrade to ESv3.5.9 and small enhancements | GREEN | Scientia released ES v3.5.9 on 8-June 2018 | ||
WP8 | Upgrade to ES v3.5.9 | Not started | upgrades to DEV, TEST and LIVE to be scheduled in Aug and Sept 2018 - task for Scientia - resources to be booked in line with UoE Phase 3 plan | ||
WP9 | Small enhancements / bug fixes for Dec 2018 main exam diet | Not started |
Issues
- Open - new re-work identified for BI Suite Universe and Reports -in progress with IS S/W Dev team and IS Service management - this risk mitigated by making Scientia ES SSRS standard reports available in LIVE for Exam Timetabling team ( as backup reporting tool)
- Closed - Scientia have released ES v3.5.9 with the fix for absolute reading time issue - not critical for Aug resits - will be applied to LIVE by Sept 2018 for Dec 2018 main exam diet
Risks
- Exams business team are one person down due to extended paternity leave for one member of the team
- The go-live period coincides with the summer holiday period, project activities are working around planned leave of project team members, with a dependency on good documentation of the new operating processes. This risk mitigated by handover between members of the project team , and avoiding too many folk on leave at the same time
Next Steps
- Phase 1 - WP3 - Calsync - complete deploy of new Exam event template to LIVE by 14-June
- Phase 1 - WP4 - Complete BI Suite Reporting - re-test of the re-work by 14-June
- Exam Timetabling business team start to use new solultion from Mon 25th June
- Post go-live scheduling support from Scientia business consultant on 4/5/6-July 2018
- Publish Aug resits exam timetable w/c 23-July 2018 - first use of the Calsync for Exams / Office365 feed
- Publish Aug resits exam timetable w/c 23-July 2018 - to the new Exam Web Timetables - first use of the new Exam Web Timetables
Milestones
see Milestone log
- Approved budget
- 470.0 days
- Activity this month
- 10.0 days
- Activity this year
- 275.0 days
- Activity to date
- 350.0 days
- Estimate to complete current year
- 60.0 days
- Estimate to complete future years
- 50.0 days