Report to 12-June 2018

Report Date
June 2018

Summary RAG for each Work package

Final deployments to LIVE done for all components, except for BI Suite Universe and Calsync

Some on-going testing and re-work for BI Suite reporting still in progress.

--

On target for first use by Exam timetabling business team from Mon 25-June

--

Phase 3 added to scope,  and the new budget split between 17-18 and 18-19 agreed with programme owner (budget holder) 

Work package RAG summary
ID Description RAG Status Comments    
Phase 1 End-to-End process for Main exam diets GREEN      
WP1 Exam Scheduler product GREEN Deployed to LIVE with copy of Reference data - Manual workarounds available for all known issues    
WP2 Student Systems Connector GREEN

Deployed to LIVE - passed final checks in pre-LIVE env 

   
WP3 Calsync Exam feed to Office365 GREEN

UAT done, some final checks in pre-Live advisable before 20-June cleardown , and Go-Live on 25-June, Calsync for Exams won't be switched-on until w/c 23-July 2018

   
WP4A BI Suite Reporting AMBER

BI Suite in TEST - second round of Universe re-work build and Report re-work build done, back to business users for another round of Testing, enough of the basic reports available for initial go-live

SSRS in TEST

   
WP4B Generic Web Timetables GREEN

Deployment to LIVE complete

   
           
Phase 2 Exceptions for Resits and Fixed date exam resits GREEN      
WP5 Resits GREEN On Track - EUGEX changes deployed to LIVE    
WP6 Fixed date exam resits GREEN some more testing to be done     
WP7 Calsync Enhancements ( from Calsync lessons learned for Teaching Timetable ) GREEN

On Track - The Critical issues with deletions has been resolved by  hotfix from supplier S2unified and is being managed by IS Service Management as part of the business-as-usual service.

 

   
           
Phase 3 Upgrade to ESv3.5.9 and small enhancements GREEN  Scientia released ES v3.5.9 on 8-June 2018    
WP8 Upgrade to ES v3.5.9 Not started upgrades to DEV, TEST and LIVE to be scheduled in Aug and Sept 2018 - task for Scientia - resources to be booked in line with UoE Phase 3 plan    
WP9 Small enhancements / bug fixes for Dec 2018 main exam diet Not started      

 

 

 

 

 

 

 

 

 

 

 

 

 

Issues

 

  • Open - new re-work identified for BI Suite Universe and Reports -in progress with  IS S/W Dev team and IS Service management - this risk mitigated by making Scientia ES SSRS standard reports available in LIVE for Exam Timetabling team ( as backup reporting tool) 
  • Closed -  Scientia have released ES v3.5.9 with the fix for absolute reading time issue  - not critical for Aug resits - will be applied to LIVE by Sept 2018 for Dec 2018 main exam diet

 

Risks

 

  • Exams business team are one person down due to extended paternity leave for one member of the team
  • The go-live period coincides with the summer holiday period, project activities are working around planned leave of project team members, with a dependency on good documentation of  the new operating processes. This risk mitigated by handover between members of the project team , and avoiding too many folk on leave at the same time

 

Next Steps

 

  • Phase 1 - WP3 - Calsync -  complete deploy of new Exam event template to LIVE by 14-June
  • Phase 1 - WP4 - Complete BI Suite Reporting - re-test of the re-work by 14-June
  • Exam Timetabling business team start to use new solultion from Mon 25th June
  • Post go-live scheduling support from Scientia business consultant on 4/5/6-July 2018
  • Publish Aug resits exam timetable w/c 23-July 2018 - first use of the Calsync  for Exams / Office365 feed
  • Publish Aug resits exam timetable w/c 23-July 2018 - to the new Exam Web Timetables - first use of the new Exam Web Timetables

 

Milestones

 

see Milestone log

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue - some re-work on WP4 BI Suite reporting continuing , will prioritise essential reporting for Aug resits , then push less urgent reporting requirements into Phase 3 before the Dec 2018 main exam diet
Change Status
Activity
Approved budget
470.0 days
Activity this month
10.0 days
Activity this year
275.0 days
Activity to date
350.0 days
Estimate to complete current year
60.0 days
Estimate to complete future years
50.0 days