Report to 21-Jan 2019

Report Date
January 2019

Key activities / Milestones since last report

Key activities since last report

  • Deployment Review mtg held with Alison Ramsay and project team 
  • Priorities agreed for wash-up tasks before project closure in Feb 2019

Milestones achieved since last report

  • Deployment Review - Done on 17-Jan

Upcoming activities / Milestones

Upcoming activities

  • IS developer booked for the BI Suite Universe re-work effort and a BI Suite universe design workshop scheduled for Wed 23-Jan
  • Complete the handover to Business as Usual Operations teams in Student Systems and IS Production by 22-Feb 
  • Develop and implement benefits review and monitoring plan
  • Close project

Upcoming milestones

  • Closure (Feb 2019)

Key activities / Milestones planned not delivered

  • None

Key risks & issues

 

Risks and Issues for escalation

  • AMBER Costs - IS Apps effort - additional unplanned effort to support BI Suite reporting  - 504d spent from Agreed budget of 495d, expect another 14d to close the project.  Expected outcome is total IS Apps effort of 518d . This is 4% variation from current allocated budget of 495d.

New / Changed Risks and Issues for information

  • AMBER Time  - limited Exams office resources available for re-testing BI Suite reports – this could push out closure date
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Amber - More re-work on Exams BI Suite universe required before handover to BAU teams
Change Status
Time
Moderate
Cost
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
495.0 days
Activity this month
2.0 days
Activity this year
61.0 days
Activity to date
504.0 days
Estimate to complete current year
14.0 days
Estimate to complete future years
0.0 days