Report to 5-Sept 2017

Report Date
September 2017

Achievements this period ( last 2 weeks to 05-09-17)

  • Data mappings reviewed to get past blocker for Scientia Developer
  • SSP have built a further new Eugex view - EUGEX_EXAM_SHEDULER_VW - to simplify the pull of Student on Exam requirement data into Exam Scheduler
  • Data mappings v1.6 shared with Scientia developer , and Scientia development re-started

 

Issues

Opened issues [These are issues still opened at the time of writing report]

  • RED showstopper - Duplicate unique identifiers in the Exam Requirements view so this data can't be imported into Exam Scheduler. Action on Andy Crossland in SSP to recommend solution

Resolved issues [These are issues resolved in the last reporting period]

 

  • Issue 9 - Expected that additional 50d funding for Exam reporting  will be approved by SA&S governance via Barry Neilson

Risks

[top 3 risks, taken from RAD log  https://uoe.sharepoint.com/sites/SEP/_layouts/15/WopiFrame.aspx?sourcedoc=%7B70804ABC-C9FA-4337-BD4F-35D3D1AB4FB8%7D&file=UoE_SAS_RAD%20Log.xlsm&action=default  under corporate format]

For escalation

Risk Id Risk Description Consequences

Inherent Impact

(1-Insignificant to 5- Severe)

Residual Impact

(1-Insignificant to 5 Severe)

Residual Probability

(1-very low to 5- Very High)

Rag

RAG movement since last month

(increased, decreased, no movement)

Mitigation Owner
1 Risk of disruption to May 2018 exam diet , when new systems are introduced   5- Severe 5-Severe AMBER     Scott Rosie
2 Risk of impact on delivery schedule if there are resource conflicts within business area, schools , Information services or within the external supplier ( Scientia Ltd consultancy and training team)   3- Medium 3-Medium 3-Medium AMBER     Jamie Thin
3 Connect Interface development - dependency on other business-as-usual projects across Student Systems and Timetabling in DEV and TEST   3- Medium 3-Medium 4-High AMBER     Jamie Thin

For information only

[risk table as above]

Next Steps

 

  • Support Scientia developer during completion of build of Student systems connector
  • Populate TEST systems with sample data , ahead of configuration and integration testing which will start on 12th Sept with Scientia delivered training to Exam Scheduler users at UoE
  • Design work on replacement Web Exam Timetables
  • Design work for new BI Suite universe
  • Design work for outgoing feed to Calsync

 

Milestones

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
RED - open issue - Scientia developer has hit showstopper retrieving data from EUGEX views - getting duplicate unique identifiers - issue with SSP to resolve
Change Status
Activity
Approved budget
280.0 days
Activity this month
34.0 days
Activity this year
34.0 days
Activity to date
111.0 days
Estimate to complete current year
167.0 days
Estimate to complete future years
0.0 days