Project Status Reports

Title Report Date Time Cost Scope Overall Change
Project Report for April April 2017 BLUE BLUE BLUE BLUE
Project Report for March March 2017 RED GREEN GREEN RED
Project Report for February February 2017 AMBER GREEN GREEN AMBER
Project Report for January January 2017 AMBER GREEN GREEN AMBER
Project Report for December December 2016 AMBER GREEN GREEN AMBER
Project Report for November November 2016 AMBER GREEN GREEN AMBER
Project Report for October October 2016 AMBER GREEN GREEN AMBER
Project Report for September September 2016 RED GREEN GREEN RED
Project Report for August 2016 August 2016 AMBER GREEN GREEN AMBER
Project Report for July 2016 July 2016 GREEN GREEN GREEN GREEN
Project Report for June 2016 June 2016 GREEN GREEN GREEN GREEN
Project Report for May 2016 May 2016 GREEN GREEN GREEN GREEN
Report for April 2016 April 2016 GREEN GREEN GREEN GREEN

Project Info

Project
Athena Swan Reporting Improvements
Code
SCE010
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Susan Duff
Project Sponsor
June Bell
Current Stage
Close
Status
Closed
Start Date
12-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Apr-2017