Project Report for March
- Report Date
- March 2017
Achievements:
- None
Issues:
- None
Next Steps:
- Draft Project Closure Report
- Close project
Milestones:
Closure milestone to be revised. Was 17/2/17. Now expected to be 14/4/17
- Approved budget
- 60.0 days
- Activity this month
- 0.0 days
- Activity this year
- 14.0 days
- Activity to date
- 34.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days