Report for March 2018
- Report Date
- March 2018
Achievements in Last Period
- JIRA 25 development complete
- Peer and Integration testing complete
- Handover to Applications Management complete
- Handed over to CAM for UAT
Issues
- None
Next Steps
- Sign off UAT
- Deployment to LIVE
Milestones
18-Apr-2018 | JIRA 25 Acceptance Testing |
24-Apr-2018 | JIRA 25 Deployment |
04-May-2018 | Closure (JIRAs 1 to 5 and 25) |
- Approved budget
- 119.0 days
- Activity this month
- 18.0 days
- Activity this year
- 74.0 days
- Activity to date
- 92.0 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days