Report for April 2018
- Report Date
- April 2018
Achievements in Last Period
- UAT continuing, a number of JIRAs have been raised and fixed.
Issues
- Business requested that UAT is extended by two weeks.
- Project is AMBER on time as deployment and closure dates have been agreed and revised in April. Resolved.
Next Steps
- Sign off UAT
- Deployment to LIVE
Milestones
04-May-2018 | JIRA 25 Acceptance Testing |
09-May-2018 | JIRA 25 Deployment |
24-May-2018 | Closure (JIRAs 1 to 5 and 25) |
- Approved budget
- 119.0 days
- Activity this month
- 7.0 days
- Activity this year
- 82.0 days
- Activity to date
- 100.0 days
- Estimate to complete current year
- 9.5 days
- Estimate to complete future years
- 0.0 days