Report for May

Report Date
May 2018

Achievements in Last Period

  • UAT signed off
  • Deployment to LIVE completed
  • Project closure achieved

Issues

  • None, now closed

Next Steps

  • None, now closed
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
119.0 days
Activity this month
6.0 days
Activity this year
88.5 days
Activity to date
107.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CAM  Degree Finders - Compliance with Legislation & Guidance
Code
STU256
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
01-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2018
Programme Priority
1
Overall Priority
Higher
Category
Compliance