Report for September 2018
- Report Date
- September 2018
Achievements
- Closure milestone updated at WIS 14-Sep-2018
- Project Manager awaiting feedback from Senior Supplier on the Project Closure Report
Issues
- None
Next steps
- Look to complete Closure report / Close Project
- Project Manager to submit a PICCL to WIS 05-Oct-2018 in order to move Closure Milestone back to 02-Nov-2018 to allow the Senior Supplier time to provide feedback
Milestones
Agreed at WIS 14-Sep-2018:
18-Jun-2018 | Launch of website |
29-Jun-2018 | Delivery sign-off |
05-Oct-2018 | Project closure |
- Approved budget
- 34.0 days
- Activity this month
- 3.3 days
- Activity this year
- 4.0 days
- Activity to date
- 26.4 days
- Estimate to complete current year
- 3.7 days
- Estimate to complete future years
- 0.0 days