Report for October 2018

Report Date
October 2018

Achievements

  • Feedback received from the Senior Supplier on the Project Closure Report 29-Oct-2018 and provided to Business Project Manager
  • Closure Review Meeting calendared 07-Nov-2018 to review feedback / look to agree project closure

Issues

  • None

Next steps

  • Project Manager to submit a PICCL to WIS 09-Nov-2018 in order to move Closure Milestone back to 30-Nov-2018 to allow time to address  feedback and agree closure
  • Look to complete Closure report / Close Project

Milestones

Agreed at WIS 02-Oct-2018:

02-Nov-2018 Project closure

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
A conflict had been raised due to the lack of availability of the Senior Supplier.  The Senior Supplier provided feedback 29-Oct-2018. This has had an impact on the timescales and ability to progress the closure report for this project, a session is now calendared to do so 07-Nov-2018.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Escalated to
Mark Ritchie, Senior Supplier
Change Commentary
A PICCL has been raised to be submitted to WIS 09-Nov-2018 to move the Closure milestone to 30-Nov-2018
Activity
Approved budget
34.0 days
Activity this month
1.0 day
Activity this year
5.0 days
Activity to date
28.1 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Careers - Student Alumni Community Networking Platform
Code
STU258
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Shelagh Green
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
09-Jan-2018
Planning Date
16-Mar-2018
Delivery Date
18-Jun-2018
Close Date
30-Nov-2018
Overall Priority
Normal
Category
Discretionary

Documentation