Report for October 2018
- Report Date
- October 2018
Achievements
- Feedback received from the Senior Supplier on the Project Closure Report 29-Oct-2018 and provided to Business Project Manager
- Closure Review Meeting calendared 07-Nov-2018 to review feedback / look to agree project closure
Issues
- None
Next steps
- Project Manager to submit a PICCL to WIS 09-Nov-2018 in order to move Closure Milestone back to 30-Nov-2018 to allow time to address feedback and agree closure
- Look to complete Closure report / Close Project
Milestones
Agreed at WIS 02-Oct-2018:
| 02-Nov-2018 | Project closure |
- Approved budget
- 34.0 days
- Activity this month
- 1.0 day
- Activity this year
- 5.0 days
- Activity to date
- 28.1 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days