End of July 2017
- Report Date
- July 2017
Achievements in Last Period
- Learn Upgrade deployed to live on 5-July as scheduled
- Building Blocks issue resolved on 20-July
- Deployment signed off by the business on July 28-Jul.
- Meeting took place 1-Aug to review any outstanding work
- Reviewed project after go Live
- One call raised with BlackBoard and depending on the result whether Support or KSR full fill this work, but it does not stop the project moving to Closure
- One specific issue with course copy it does not affect any other issues or prevent the project from closing
- Started closure report
Issues
- No issues
Next Steps
- One JIRA that support are progressing connected with TEST.
- Complete Closure Report
- Close Project
RAG Status:
GREEN
Milestones
| 11-Aug-2017 | Close |
- Approved budget
- 71.0 days
- Activity this month
- 20.0 days
- Activity this year
- 87.0 days
- Activity to date
- 87.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 1.0 day