Report for December2017

Report Date
December 2017

Achievements in Last Period

  • TAD update begun. 

Issues

  • Project Manager departed due to illness.  New project manager inducted. 
  • Review of project plan and estimates to complete under way.

 

Next Steps 

  • Re-baseline project plan and confirm assignment of resources. 
  • Commence delivery.  

The project is reporting AMBER.

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Project plan is being re-baselined, which should return status to GREEN w/c 29/01. No action required from SMT.
Change Status
Activity
Approved budget
59.0 days
Activity this month
2.8 days
Activity this year
12.9 days
Activity to date
11.5 days
Estimate to complete current year
48.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Learn Database Migration to Oracle 12
Code
TEL048
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Nicholas Graham
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
16-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Compliance