Report for January 2018
- Report Date
- January 2018
Achievements in Last Period
- TAD updated.
- Development DB migration and load begun.
- Project re-planned.
- Resources identified and committed.
- Revised cutover dates identified and agreed with customer community.
Issues
- There is an issue regarding project plan - replanned milestones need to be hardened by protecting resources. This will be achieved by requesting WIS to raise project priority to 'Higher'.
Next Steps
- Agree upgrade to project priority.
- Complete development and integration test.
The project is reporting AMBER.
- Approved budget
- 59.0 days
- Activity this month
- 9.6 days
- Activity this year
- 21.1 days
- Activity to date
- 21.1 days
- Estimate to complete current year
- 38.9 days
- Estimate to complete future years
- 0.0 days
