Report for January 2018

Report Date
January 2018

Achievements in Last Period

  • TAD updated.
  • Development DB migration and load begun.
  • Project re-planned. 
  • Resources identified and committed. 
  • Revised cutover dates identified and agreed with customer community.

Issues

  • There is an issue regarding project plan - replanned milestones need to be hardened by protecting resources.  This will be achieved by requesting WIS to raise project priority to 'Higher'. 

Next Steps 

  • Agree upgrade to project priority.   
  • Complete development and integration test.    

The project is reporting AMBER.

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue - There is an issue regarding project plan - replanned milestones need to be hardened by protecting resources.  This will be achieved by requesting WIS to raise project priority to 'Higher'. 
Change Status
Activity
Approved budget
59.0 days
Activity this month
9.6 days
Activity this year
21.1 days
Activity to date
21.1 days
Estimate to complete current year
38.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Learn Database Migration to Oracle 12
Code
TEL048
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Nicholas Graham
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
16-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation