Report for May 2018

Report Date
May 2018

Achievements in Last Period

  • Replacement PM started 14/05/18.
  • Consultation exercise complete.
  • New templates produced.

Issues

  • Significant changes to project scope upcoming.

Next Steps

  • Handover of Business Lead.
  • Review of actions for Project Board.
  • Agreement on scope changes.

 

Project RAG status is currently RED due to significant upcoming scope changes & unknown impact on cost & timescales. No escalation required at this time.

Milestones

22-Jun-2018 Agree Terms of Reference for Pilot(s)
13-Jul-2018 Recommendations Report
14-Dec-2018 Complete Pilot(s)
25-Jan-2019 Review Pilot(s) and Agree plan for Rollout
25-Jan-2019 Agree Communications Plan
25-Jan-2019 Agree Support & Training Plan
24-May-2019 Institutional Templates Available
28-Jun-2019 Complete Rollout
30-Aug-2019 Post Rollout Support
13-Sep-2019 Delivery Sign Off Review
27-Sep-2019 Project Closure
Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
RAG Commentary
Change - Project RAG status is currently RED due to significant upcoming scope changes & unknown impact on cost & timescales. No escalation required at this time.
Change Status
Activity
Approved budget
160.0 days
Activity this month
13.5 days
Activity this year
31.3 days
Activity to date
31.3 days
Estimate to complete current year
60.3 days
Estimate to complete future years
71.7 days

Project Info

Project
VLE Standards
Code
TEL049
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Laura Woods-Dunlop
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Withdrawn
Start Date
16-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
24-Aug-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation