Report for May 2018
- Report Date
- May 2018
Achievements this period
- Upgraded Moodle to 3.4.2 in DEV and TEST
- Completed Behat feasibility including decommissioning and report of findings/steps
- Proved Office 365 connection with Moodle
- Reviewed 3.4.2 in DEV
- Completed 'internal' UAT on TEST
- Completed staff and student led UAT on TEST
Issues
-
The DLAM team decided to upgrade to Moodle 3.4.2 in order to bring in new fixes and GDPR plugins. The additional IS Applications effort required for the change in scope was 5 days, which was secured. The upgrade has been completed and not impacted the overall delivery timeline. DLAM will get benefits of the recaptcha fix, other fixes and GDPR plugins.
Next Steps
- Collate UAT feedback
- Implement fixes following feedback
- Compile feedback from UAT
- Implement fixes (where required)
- Load testing
- Full Disaster Recovery test
- Start deployment checklists
- Approved budget
- 91.0 days
- Activity this month
- 12.1 days
- Activity this year
- 56.3 days
- Activity to date
- 56.3 days
- Estimate to complete current year
- 33.7 days
- Estimate to complete future years
- 0.0 days
