Report for June 2018
- Report Date
- June 2018
Achievements this period
- Upgraded Moodle to 3.4.3 in DEV and TEST
- Collated UAT feedback
- Implemented fixes following feedback
- Completed UAT
Issues
-
The DLAM team decided to upgrade to Moodle 3.4.3 in order to fix an emerging security issue with 3.4.2. The additional IS Applications effort was absorbed within the existing project budget. The upgrade has been completed and not impacted the overall delivery timeline.
-
Neither the DR test nor load testing were completed the week commencing 25th Jun; for load testing this was because a Dev Tech resource remained on an overrunning booking on DTI026. Following discussions with the key stakeholders it was agree to move the load testing to 2nd-3rd July. The Business Lead prefers to stick with the delivery timeline for the LIVE deployment, so a further decision around delivery will be made around the 4th July to see what has arisen from the load testing. At that stage there will either be no issues identified or some issues to fix, if the latter then a decision can be made between going ahead with known issues or pushing the deployment date back. As there is some uncertainty at the time of writing this report, I have marked the project as AMBER this month.
-
* UPDATE 6TH JULY -reverted to GREEN as load testing was completed with no issues arising
Next Steps
- Full Disaster Recovery test
- Complete deployment checklists
- Deploy to LIVE (10th July)
- Approved budget
- 91.0 days
- Activity this month
- 7.6 days
- Activity this year
- 64.4 days
- Activity to date
- 64.4 days
- Estimate to complete current year
- 26.6 days
- Estimate to complete future years
- 0.0 days