Achievements this period

  • Completed load testing
  • Undertook full Disaster Recovery test
  • Completed deployment checklists
  • Deployed Moodle 3.4.3 to LIVE (10th July)

Issues

  • A code error has been diagnosed with the Turnitin two plugin for Moodle in the LIVE environment, which has impacted the display of column data for markers on assignments.  DLAM have reported the issue to Turnitin and it is being investigated.  Once a resolution has been established, this will be implemented by the Moodle Service team after the project has closed.

  • DLAM found a known issue in Moodle 3.4.3 which accounts for a notifications error, which will be documented and be resolved by Moodle Service team (there is a fix available in Moodle 3.4.4).  The error has a workaround but impacts user experience.

  • DLAM cannot run TELSMI extract in LIVE environment - Apps Management will investigate and resolve.

  • All outstanding issues agreed by DLAM to be picked up by Service so aren't required to be resolved within the project

Next Steps

  • None - project closed on 3rd August
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
91.0 days
Activity this month
15.6 days
Activity this year
80.0 days
Activity to date
80.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Moodle Upgrade (17/18)
Code
TEL051
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Mark Findlay
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
12-Jan-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Aug-2018