Report for July 2018
- Report Date
- July 2018
Achievements this period
- Completed load testing
- Undertook full Disaster Recovery test
- Completed deployment checklists
- Deployed Moodle 3.4.3 to LIVE (10th July)
Issues
-
A code error has been diagnosed with the Turnitin two plugin for Moodle in the LIVE environment, which has impacted the display of column data for markers on assignments. DLAM have reported the issue to Turnitin and it is being investigated. Once a resolution has been established, this will be implemented by the Moodle Service team after the project has closed.
-
DLAM found a known issue in Moodle 3.4.3 which accounts for a notifications error, which will be documented and be resolved by Moodle Service team (there is a fix available in Moodle 3.4.4). The error has a workaround but impacts user experience.
-
DLAM cannot run TELSMI extract in LIVE environment - Apps Management will investigate and resolve.
-
All outstanding issues agreed by DLAM to be picked up by Service so aren't required to be resolved within the project
Next Steps
- None - project closed on 3rd August
- Approved budget
- 91.0 days
- Activity this month
- 15.6 days
- Activity this year
- 80.0 days
- Activity to date
- 80.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days