Report for July 18

Report Date
July 2018

Achievements in Last Period

  • Rolled back to CU2 and after testing was able to  bring RAG down to AMBER as agreed  - see risk 1
  • Deployed successfully on 17 July with CU2  - Comms on issues sent out by Steph - RAG now GREEN
  • Deployment review held 31 July 18
  • Project closure approved by project team 31 July 18
  • Closure approved by WIS 3 August 18

Issues

  • Same issue deploying to LIVE as issue on deploying to TEST - Nik rebuilt servers and brought them into same firewall as other servers

Next Steps

  • None

Milestones

None

 

RAG commentary

Project is BLUE -closed

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
72.0 days
Activity this month
24.0 days
Activity this year
71.9 days
Activity to date
71.9 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Learn Annual Upgrade
Code
TEL053
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Mark Findlay
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
08-Jan-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Aug-2018
Overall Priority
Higher
Category
Compliance