Report for July 18
- Report Date
- July 2018
Achievements in Last Period
- Rolled back to CU2 and after testing was able to bring RAG down to AMBER as agreed - see risk 1
- Deployed successfully on 17 July with CU2 - Comms on issues sent out by Steph - RAG now GREEN
- Deployment review held 31 July 18
- Project closure approved by project team 31 July 18
- Closure approved by WIS 3 August 18
Issues
- Same issue deploying to LIVE as issue on deploying to TEST - Nik rebuilt servers and brought them into same firewall as other servers
Next Steps
- None
Milestones
None
RAG commentary
Project is BLUE -closed
- Approved budget
- 72.0 days
- Activity this month
- 24.0 days
- Activity this year
- 71.9 days
- Activity to date
- 71.9 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days