May 2017
- Report Date
- May 2017
Achievements
- Morna Findlay taken on Project Manager role (from Sheila Fraser)
- Project planning approved
- Update to spring framework was required to enable upgrade to supported tomcat and apache versions
- Project build stage completed
- Project reviewed, re-estimated and new milestones proposed
Issues
- Delay to build sign off (due to requirement to update spring framework) requires new milestones and new estimate to be approved.
- EDG is now running on unsupported software ( tomcat)
Next steps
- Approval of new milestones and estimate
- Upgrade and refresh of TEST
- Carry out user acceptance testing and sign off TEST
Milestones (proposed)
| 09-Jun-2017 | TEST upgrade of apache tomcat complete |
| 16-Jun-2017 | User acceptance test post apache tomcat upgrade |
| 03-Jul-2017 | LIVE upgrade apache tomcat |
| 17-Jul-2017 | Deployment sign-off review |
| 24-Jul-2017 | Closure |
- Approved budget
- 20.0 days
- Activity this month
- 9.0 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days