May 2017

Report Date
May 2017

Achievements

  • Morna Findlay taken on Project Manager role (from Sheila Fraser)
  • Project planning approved
  • Update to spring framework was required to enable upgrade to supported tomcat and apache versions
  • Project build stage completed
  • Project reviewed, re-estimated and new milestones proposed

Issues

  • Delay to build sign off (due to requirement to update spring framework) requires new milestones and new estimate to be approved.
  • EDG is now running on unsupported software ( tomcat)

Next steps

  • Approval of new milestones and estimate
  • Upgrade and refresh of TEST
  • Carry out user acceptance testing and sign off TEST

Milestones (proposed)

09-Jun-2017     TEST upgrade of apache tomcat complete
16-Jun-2017     User acceptance test post apache tomcat upgrade
03-Jul-2017     LIVE upgrade apache tomcat
17-Jul-2017     Deployment sign-off review
24-Jul-2017     Closure

 

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Change: New milestones and estimate to be approved
Change Status
Activity
Approved budget
20.0 days
Activity this month
9.0 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Edinburgh Global Directory End of Life Compliance
Code
USG004
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
14-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jul-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance