June 2017

Report Date
June 2017

Achievements

  • Build signoff achieved
  • Refresh of TEST  from LIVE achieved
  • Acceptance signoff achieved
  • Delivery achieved

Issues

  • None - AMBER due to forthcoming reduction of estimate of work to complete, within 20% of current estimate (26d).

Next steps

  • Deployment signoff
  • Closure

Milestones 

17-Jul-2017     Deployment sign-off review
24-Jul-2017     Closure

 

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
RAG Commentary
AMBER - CHANGE - estimate will decrease as no UAT issues identified.
Change Status
Activity
Approved budget
20.0 days
Activity this month
9.0 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Edinburgh Global Directory End of Life Compliance
Code
USG004
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
14-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jul-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance