June 2017
- Report Date
- June 2017
Achievements
- Build signoff achieved
- Refresh of TEST from LIVE achieved
- Acceptance signoff achieved
- Delivery achieved
Issues
- None - AMBER due to forthcoming reduction of estimate of work to complete, within 20% of current estimate (26d).
Next steps
- Deployment signoff
- Closure
Milestones
| 17-Jul-2017 | Deployment sign-off review |
| 24-Jul-2017 | Closure |
- Approved budget
- 20.0 days
- Activity this month
- 9.0 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days