Report for July 2021
- Report Date
- July 2021
Achievements in last period
- Ongoing support of DPOs and survey respondents while survey is available
- Regular checking and analysis of submissions
- Chasing and prompting of areas with zero/low returns
- Plans made for eventual analysis and report
Issues
- It has transpired that some areas have not distributed the survey to colleagues
- DPO has decided that the completion date should be extended to allow for catch up
Next steps
- Support respondents and DPO staff during lifetime of survey
- Monitor responses and conduct initial analysis
- Update project milestones
Milestones (to be updated)
Execute | Survey end date | 30-Jul-2021 |
Deliver | Delivery of Project Outcomes | 13-Aug-2021 |
Close | Project Closure | 27-Aug-2021 |
- Approved budget
- 40.0 days
- Activity this month
- 5.5 days
- Activity this year
- 23.7 days
- Activity to date
- 23.7 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 10.0 days