Organisation

Work/Task Breakdown

  • Initial planning meeting
  • User story writing
  • Estimation meeting
  • R&D effort
  • 1 development iteration

Resources Skills and Cost

Total cost is 30 days

  • 2 days planning
  • 5 days r&d effort
  • 21 days for development. This amounts to 1 iteration.
  • 2 days project management support

Project Governance

Standard apps procedures will be used for this project

 

Project Info

Project
EdWeb Collaboration Pilot and Feature Development
Code
UWP015
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
30-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
2
Overall Priority
Normal
Category
Discretionary