This is a core funded compliance project with a required budget of 121d. 

Impact and Dependencies

  • The project timeline has been developed to enable the required final release date to be met, therefore once the schedule is approved, any changes due to unforeseen circumstances may affect dependant risks and issues.
  • Implementation plan designs and accompanying documentation listed in the plan before implementation can commence.  Delays aligned to this would impact final release date.
  • Content will be spidered using web crawler and APIs, there is therefore a dependency to current and future UoE APIs.  
  • Consultation and engagement has been built into the project timeline to ensure requirements can be established and user experience priorities addressed.

Risks

See risk register

Project Info

Project
Implementation of procured University search service
Code
UWP016
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Emma Mcnab
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Jun-2017
Planning Date
06-Oct-2017
Delivery Date
13-Dec-2018
Close Date
25-Jan-2019
Programme Priority
3
Overall Priority
Normal
Category
Compliance