Achievements Last Period.

All activities relating to development , testing and deployment completed to schedule.

Issues.

The deployment activities did not achieve the required effect of redirecting the LIVE URL to the new code. This will require further investigation. Investigations into the issue have been hampered by annual leave by techical staff involved.

Additional 3 days to be requested for investigations and closure activities

Next steps.

Work with App Management and CAMS to determine the correct deployment route and re-plan the deployment schedule and project closure. This will be picked up w/c 10/09 due to annual leave in App Management.

Milestones

Target date

Title

03-Aug-2012

ASOR - Testing carried out by C&M.

16-Aug-2012

Go-Live rollout.

23-Aug-2012

DSOR

27-Aug-2012

Project Closure

 

Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
21.0 days
Activity this month
3.0 days
Activity this year
3.0 days
Activity to date
21.0 days
Estimate to complete current year
3.0 days
Estimate to complete future years
3.0 days

Project Info

Project
Polopoly Updates for Cookie Legislation
Code
UWS001
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Stephen Conlon
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
30-May-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
24-Oct-2012