June 2015

Report Date
June 2015

 

The project has delivered the second, minor upgrade via bamboo - no issues post deployment.

It will now close

 

Achievements in Last Period

 

  • deliver to live - done
  • despoyment sign-off - done
  • closure - in progress

Issues

  • no medium or high risks
  • no issues

Next Steps

  • closure w/c 29th June

 

Milestones

 

30-Jun-201524-Jun-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
145.0 days
Activity this month
2.0 days
Activity this year
144.0 days
Activity to date
144.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days