April 2015

Report Date
April 2015

 

After a number of channels failed after deployment, the build, QA and delivery of the minor upgrade via Bamboo has been replanned to ensure better testing and channel owner engagement in the QA process, to provide production support and service owners confidence in the technology.

The effort in resolving issues has pushed the estimation for total effort beyond the current budget, and with LTW requesting that Project Manager takes over UAT lead and coordiation then the estimate woudl increase further.  

Achievements in Last Period

  • Acceptance sign-off for Minor Upgrade Delivery -completed
  • Delivery Minor Upgrade and the last two channels - completed
  • Build sign-off for Minor Upgrade Delivery - completed
  • Decide if PM to lead UAT and resolve budget issue that may arise - completed

Issues

  • no medium or high risks

Next Steps

  • Acceptance sign-off

 

Milestones

 

01-May-2015Build Sign-Off - Minor Upgrade via Bamboo
27-May-2015Acceptance Sign-Off - Minor Upgrade via Bamboo
11-Jun-2015Delivery of Minor Version Upgrade
23-Jun-2015DSOR
30-Jun-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
130.0 days
Activity this month
10.0 days
Activity this year
138.0 days
Activity to date
138.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days