May 2015

Report Date
May 2015

 

The project is well on course to sign-off the acceptance formally on the 4th June.

The channels have been QA'd by most channel owners, and the progress can be checked at this page

https://www.wiki.ed.ac.uk/pages/viewpage.action?pageId=258485970

with most channels tested with no issue, or with acceptable issues, and UAT test period came to an end on the 29th as planned.

The project budget was increased by 15 days to 145 days, covering the post-delivery fixes for channels.

 

Achievements in Last Period

  • Acceptance sign-off - completed

Issues

  • no medium or high risks
  • no issues

Next Steps

  • deliver to live
  • despoyment sign-off
  • closure

 

Milestones

 

27-May-201527-May-2015Acceptance Sign-Off - Minor Upgrade via Bamboo
11-Jun-201504-Jun-2015Delivery of Minor Version Upgrade
23-Jun-201518-Jun-2015DSOR
30-Jun-201524-Jun-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
145.0 days
Activity this month
10.0 days
Activity this year
141.0 days
Activity to date
141.0 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days