Project Status Reports

Title Report Date Time Cost Scope Overall Change
July report July 2025 GREEN GREEN GREEN BLUE Within Tolerance
June report June 2025 GREEN GREEN GREEN GREEN Within Tolerance
May 2025 progress report May 2025 GREEN GREEN GREEN GREEN Within Tolerance
April 2025 report April 2025 GREEN GREEN GREEN GREEN Within Tolerance
Report for March 2025 March 2025 GREEN GREEN GREEN GREEN
Report for February 2025 February 2025 GREEN GREEN GREEN GREEN Within Tolerance
Report for January 2025 January 2025 GREEN GREEN GREEN GREEN Within Tolerance

Project Info

Project
The Role of Profiles
Code
WPS021
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Emma Horrell
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
04-Jan-2025
Planning Date
20-Feb-2025
Delivery Date
01-Jul-2025
Close Date
31-Jul-2025
Programme Priority
4
Overall Priority
Normal
Category
Discretionary

Documentation