Report for July 2019
- Report Date
- July 2019
Report by Muriel Mewissen on behalf of David Perry and Anthony Davie (MVMRes Programme Managers), for Charles ffrench-Constant and Paul McGuire (MVMRes Programme Owners), Sheila Fraser (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
-
Institute IT meetings / Service Review meetings.
-
College Research Support Network (RSN) meeting.
-
College Research Committee
-
Excerpts taken into CSG report
Section One: Programme Commentary, RAG and Resources Update
Commentary
During July, MVM314: SEBI - Data Collection and Modelling was formally re-started and successfully deliver the Migration of local Tableau platform to Hosted service.
A new project was also added to the programme, MVM316: Fragile X Registry website. It will support the work of the Patrick Wild Centre and provide them with an online registry of people with fragile x syndrome, and their families.
The other three projects continued to be delayed due to PM and stakeholder availability. They are reporting an AMBER status and will all continue into next year. It is expected that they will be completed in 2019/20 Q1.
The overall status of the MVMRes programme is AMBER.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - July 2019
Section Two: Projects Not Started
No additional project will be started this session.
Section Three: Projects in Progress
MVM302: Compute and High Performance Compute Strategy - RAG Status: AMBER Report by Barry HorneAchievements this period
Issues
Next Steps
|
MVM305: Flexible Server hosting - RAG Status: SUSPENDED Report by Muriel MewissenAchievements this period
Issues
Next Steps
|
MVM308: Research computing induction - RAG Status: AMBER Report by Paul De'AthAchievements this period
Issues
Next Steps
|
MVM311: CMVM Data Storage Strategy - RAG Status: AMBER Report by Geoff CropleyAchievements this period
Next Steps
|
MVM314: SEBI - Data Collection and Modelling - RAG Status: GREEN Report by Colin WattAchievements this period
Next Steps
|
MVM316: Fragile X Registry website - RAG Status: GREEN Report by Sophie MilnerAchievements this period
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info |
Project Manager's Commentary |
---|---|
MVM309 Scientific administration process enhancements | Decision to withdrawn the project has been agreed at the Programme Review Monthly Meeting - March 2019. The business is not yet ready for this and a lot of background is needed in several areas before this work could start. |
MVM315: REACH |
This project was started in July 2017 nd was closed on the 21 December 2018. The Completion Report is available to view. |
This project was started in April 2017 and was closed on the 28 September 2018. The Completion Report is available to view. |
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
24 June 2019 | Programme Review Monthly Meeting - June 2019 |
23 May 2019 | Programme Review Monthly Meeting - May 2019 |
1 May 2019 | Programme Review Monthly Meeting - April 2019 |
27 March 2019 | Programme Review Monthly Meeting - March 2019 |
28 February 2019 | Programme Review Monthly Meeting - February 2019 |
29 January 2019 | Programme Review Monthly Meeting - January 2019 |
21 November 2018 | Programme Review Monthly Meeting - November 2018 |
30 October 2018 | Programme Review Monthly Meeting - September 2018 |
27 September 2018 | Programme Review Monthly Meeting - August 2018 |
24 July 2018 | Programme Review Monthly Meeting - July 2018 |