Organisation

 

Work/Task Breakdown

 

TaskEffort (Days)
Project Management5
Design of CMDB  and CI structure5
Process and CMDB structure Documentation5
MigrationPlan5
Migration from MCC to CMDB18
Closure2

Resources Skills and Cost

 

Total of 40 days cost, 10 in 13/14 and 30 in 14/15.

The main resources will involve Iain Fiddes and Stefan Kaempf during the design phase, while migration will involve Production Management and Development Technology staff. Service Management (Matt Beilby and Alex Carter will be involved in reviewing both design and migration. Robert Gormley from USD will be the main non IS Applications resource involved.

 

Project Info

Project
Migration from Change Control to CMDB
Code
APP004-26
Project Manager
Stefan Kaempf
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
29-May-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Jan-2017