Monthly Report
Monthly Report
Report Date
February 2017
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
LST has passed this to an external AV PM to run due to our current workload. This project is due for completion around March 2018 so time is not yet an issue but the Architects need design drawings now. We have not had a clear steer on cost and there may be more then the 5 rooms we know about requiring AV.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days
This article was published on
Mar 9, 2017
Project Info
Project
Bayes Institute (DTI)
Code
AV2556
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Management Office
ISG PMO
Project Manager
Stephen Dishon
Project Sponsor
Anna Stamp
Current Stage
Close
Status
Closed
Start Date
01-Jan-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Aug-2018
More project information
Documentation
Initiate
No documents
Plan
Project Brief
Execute
No documents
Deliver
No documents
Close
Closure Report
Other