Monthly Report

Report Date
June 2018
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Issue: There is a clear programme for the AV which started on the 4th June 2018 with the ground and 1st floor. We have been unable to get much works done as these floors are still not really finished. The AV contractor has done as much as they can over all 5 floors and whilst I have few concerns just now about being finished for September, we may have some outstanding issues. The plan to move staff in from the start of August is questionable but we do have a whole month for things to improve.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Bayes Institute (DTI)
Code
AV2556
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Management Office
ISG PMO
Project Manager
Stephen Dishon
Project Sponsor
Anna Stamp
Current Stage
Close
Status
Closed
Start Date
01-Jan-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Aug-2018

Documentation