Priority, Funding and Dependencies

Priority and Funding

  • A discretionary, sponsor funded, in-year project - IS Applications Priority 2

Dependencies

  • Approval from UHRS to use staff data from HR system
  • Provision of existing staff data and existing course catalogue data from pilot teams
  • Totara LMS integration with EASE (via Shibboleth)
  • Resources available to develop an automated feed to manage CSG starters, leavers and changes in staff data (and compatibility with defined organisation hierarchy)
  • Approval for use of Events Booking application data from Service Owner
  • Availability of Business Leads to promote and manage pilot in their respective business units
  • Reporting within Totara LMS available to deliver requirement around reporting on transparent spend
  • Development of integration with Event Booking application in Phase 2 would require additional funding
  • Support from IS Applications for wider rollout would require additional funding

Project Info

Project
Totara LMS Pilot
Code
CSG011
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Charles Hill
Current Stage
Close
Status
Closed
Start Date
09-Dec-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Jan-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary