Work/Task Breakdown

No P A Task Type
T010 ESPA Website future      
T020     CSG012 - Project Management  
T030        CSG012 - Project Managing Task
T040        CSG012 - PM support from CSG programme management Task
T050        CSG012 - PM support from USG programme management Task
T060        CSG012 - Quality Assurance Task
T130     CSG012 - Planning   
T140        CSG012 - Planning Task
T150        CSG012 - Sign-off meetings Task
T150        CSG012 - Weekly meetings Task
T160     CSG012 - Discovery & Systems Analysis  
T170        CSG012 - UX Workshops planning Task 
T180        CSG012 - UX Workshops, delivery and review Task
T190        CSG012 - Back-end DB and data source review Task
T200        CSG012 - Requirements for reporting Task
T210        CSG012 - Infrastructure review and fitness assessment Task
T190     CSG012 - Systems Design  
T200        CSG012 - Model existing data into target CMS / object handler Task
T250 Build      
T260     CSG012 - Build  
T270        CSG012 - Building dev env, repositories etc Task
T280        CSG012 - Build new data entities in Drupal to replace SQL server & export to code Task
T290        CSG012 - Build replacement importers for ResearchFish Task
T300        CSG012 - Reports / exports (low=2; med=5;hi=7) Task
T310        CSG012 - Implement new mobile-first theme Task
T320        CSG012 - Implement new IA, search, nav etc from workshops Task
T330     CSG012 - Test & Acceptance  
T340        CSG012 - Set up test environment and instances Task
T350        CSG012 - Deploy code into test env Task
T360        CSG012 - Integration / system test Task
T370        CSG012 - User Acceptance Test Task
T380     CSG012 - Deployment  
T390        CSG012 - Set up test environment and instances  
T400        CSG012 - deploy code into live environment Task
T410        CSG012 - Post-implementation support (by dev?) Task
T420        CSG012 - handover to service managenent / application management Task
T430        CSG012 - Project Closure report Task
T440     CSG012 - Project Milestones  
T450        CSG012 - Project Brief sign-off Milestone
T460        CSG012 - Planning sign-off Milestone
T470        CSG012 - Analysis / UX Reqs definition sign-off Milestone
T480        CSG012 - Back-end design sign-off Milestone
T490        CSG012 - Development Build sign-off Milestone
T500        CSG012 - Install in test Milestone
T510        CSG012 - Integration / system test sign-off Milestone
T520        CSG012 - User Acceptance Test sign-off Milestone
T530        CSG012 - Deploy to Live environment Milestone
T540        CSG012 - Deployment handover to support Milestone
T550        CSG012 - Post-implementation handover to support sign-off Milestone
T560        CSG012 - Project Closure Milestone

 

Resources, Skills and Costs

The core project team will consist of the following individuals and roles:

 

Eliane Reid - Project Sponsor

Marie Dupar - Senior User

Neil Allison - Web UX Manager

Duncan Davidson - Drupal  Developer (Contracted)

Andrew Habgood - Technical QA.  

Nicholas Graham - Project Manager

 

Project Governance

The project will follow the standard Information Services model.

Resources from the following teams are required to deliver this project:

IS Apps Section Team  Estimate (Days) Estimate (16/17 Days) Estimate (17/18 Days)
         
Project Services  Project Services  42.3 30.3 12.0
  Other 6.0 4.0 2.0
Development Services Development Team  83.5 23.5 60.0
         
  Configuration Team       
         
  Development Technology  2.5 1.5 1.0
         
Production Management  Applications Management  5.0 1.0 4.0
         
  Technology Management  0.5 0.0 0.5
         
Service Management  Delivery and Integration  2.0 0.0 2.0
         
  Multimedia      
         
Directors Office Directors Office 0.0 0.0 0.0
         
         
  Total Days 141.8 60.3 81.5
Non IS-APPS        
WEB UX WEB UX 11 11 0

Project Stakeholders

Name Business area Role
Alex Carter Service Management Senior Supplier
Anne Finnan Applications Service Group - CSG Applications Service
Bill Lee Development Services Resource Manager
Eliane Reid ESPA Manager Project Sponsor - core team member.
Heather Larnach Technology Management Production Manager
Iain Fiddes Development Services Development Services
Jo Blackmore Director's Office Resource Manager
Mark Ritchie Project Services Head of Project Services
Neil Allison IT Services User Experience Manager - core team member.
Nicholas Graham Project Services Project Manager - core team member.
Nikki Stuart Project Services - CSG Portfolio Manager
Paul McNulty Development Services Resource Manager
Sheila Fraser Project Services - USG & SCE Expert input based on living and working across Africa for several years
Marie Dupar ESPA Comms Senior User - core team member

 

Project Estimations

The project estimation log can be found here:

https://www.projects.ed.ac.uk/unpublished/project/csg012/estimations

 

 

Project Info

Project
ESPA Website
Code
CSG012
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Nikki Stuart
Project Sponsor
Eliane Reid
Current Stage
Close
Status
Closed
Start Date
11-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal
Category
Discretionary