Report for October 2017
- Report Date
- October 2017
Achievements in the last period
- Rohallion engagement confirmed. Development begun.
- QA by IS Development Services begun.
- Demonstration of desktop re-theming delivered to schedule 30/10/17.
- Customer proposed re-focusing UAT activities on content and editorial work by ESPA team.
- Preparation for cutover to live service on 22/11/17 remains on schedule.
- Drupal support responsibilities agreed.
Issues
-
None.
Next steps
- Completion of increment 1 development work.
- Sign-off by customer stakeholder.
- Completion of live environment preparation.
- Cutover of delivered website to schedule on 22/11/17.
Milestones
| Target Date |
Previous Date | Title | Stage | Complete | |
|---|---|---|---|---|---|
| 21-Apr-2017 | No date available | Brief sign-off | Initiate | Yes | |
| 09-Jun-2017 | 21-Apr-2017 | Planning sign-off | Plan | Yes | |
| 18-Aug-2017 | 04-Jul-2017 | Discovery end: UX Requirements and back-end analysis defined & signed off | Analyse | Yes | |
| 18-Aug-2017 | 04-Jul-2017 | Back-end design sign-off | Analyse | Yes | |
| 10-Nov-2017 | 24-Jul-2017 | Development Build Sign-off | Build | No | |
| 13-Nov-2017 | 25-Jul-2017 | Install in Test | Integrate | No | |
| 14-Nov-2017 | 27-Jul-2017 | Integration / system test sign-off | Integrate | No | |
| 22-Nov-2017 | 04-Aug-2017 | User Acceptance sign-off | Accept | No | |
| 22-Nov-2017 | 07-Aug-2017 | Deploy to live | Deliver | No | |
| 22-Nov-2017 | 08-Aug-2017 | Deployment / handover to support sign-off | Deliver | No | |
| 22-Nov-2017 | 22-Aug-2017 | Post-implementation support sign-off | Deliver | No | |
| 30-Mar-2018 | 29-Aug-207 | Project Closure | Close | No |
- Approved budget
- 154.0 days
- Activity this month
- 5.7 days
- Activity this year
- 10.6 days
- Activity to date
- 42.3 days
- Estimate to complete current year
- 89.8 days
- Estimate to complete future years
- 0.0 days