Report for October 2017

Report Date
October 2017

Achievements in the last period

  • Rohallion engagement confirmed.  Development begun. 
  • QA by IS Development Services begun.
  • Demonstration of desktop re-theming delivered to schedule 30/10/17. 
  • Customer proposed re-focusing UAT activities on content and editorial work by ESPA team. 
  • Preparation for cutover to live service on 22/11/17 remains on schedule. 
  • Drupal support responsibilities agreed.  

Issues

  • None.      

Next steps

  • Completion of increment 1 development work. 
  • Sign-off by customer stakeholder. 
  • Completion of live environment preparation. 
  • Cutover of delivered website to schedule on 22/11/17.

Milestones

 

Target Datesort descending Previous Date Title Stage Complete  
21-Apr-2017  No date available  Brief sign-off Initiate Yes

 view

09-Jun-2017  21-Apr-2017  Planning sign-off Plan Yes

 view

18-Aug-2017  04-Jul-2017 Discovery end: UX Requirements and back-end analysis defined & signed off Analyse Yes

 view

18-Aug-2017  04-Jul-2017 Back-end design sign-off Analyse Yes

 view

10-Nov-2017  24-Jul-2017 Development Build Sign-off Build No

 view

13-Nov-2017  25-Jul-2017 Install in Test Integrate No

 view

14-Nov-2017  27-Jul-2017 Integration / system test sign-off Integrate No

 view

22-Nov-2017  04-Aug-2017 User Acceptance sign-off Accept No

 view

22-Nov-2017       07-Aug-2017 Deploy to live Deliver No

 view

22-Nov-2017 08-Aug-2017 Deployment / handover to support sign-off Deliver No

 view

22-Nov-2017  22-Aug-2017 Post-implementation support sign-off Deliver No

 view

30-Mar-2018  29-Aug-207 Project Closure Close No

 view

   
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
154.0 days
Activity this month
5.7 days
Activity this year
10.6 days
Activity to date
42.3 days
Estimate to complete current year
89.8 days
Estimate to complete future years
0.0 days

Project Info

Project
ESPA Website
Code
CSG012
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Nikki Stuart
Project Sponsor
Eliane Reid
Current Stage
Close
Status
Closed
Start Date
11-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal
Category