Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
-
[IS Apps] Corporate Planner WS2008 servers (3) upgraded
-
[CSE] GEOS WS2008 servers (4) decommissioned
- [CMVM] ECRF WS2008 test server (1) upgrade in progress
- [ITI] Replacement VMs for 3 ITI CIS WS2003 servers in test
- Request with Software Services to provide extended support costs
Risks/Issues
-
Service owners/system administrators may not initiate remediation work on applications running on WS2003/2008 servers
-
End of support date for WS2008 is 14/01/2020 with 93 servers still operational
-
44 WS2008 servers will miss EOS date with 17 servers with no planned upgrade or retirement date
-
- Apps Ed rollout delayed January, at least, put planned decommissioning for DST servers at risk
Next steps
- [ITI] ESW systems WS2008 servers (6) to be upgraded; planned 12/2019
-
[EDINA] WS2008 application servers (5) to be decommissioned; planned 12/2019
-
[CAHSS] SPS WS2008 servers (22) to be decommissioned; planned 12/2019
-
[CAHSS] Business School one server to be upgraded by 12/2019
-
[EDINA] WS2008 application servers (3) to be decommissioned; planned 12/2019
-
[IS Apps] Parking WS2008 servers (2) to be decommissioned; planned 12/2019
-
[Digital Library] WS2008 application servers (2) to be retired; planned 01/2020
-
[ITI] DST W7 RDS/VDS/SCCM WS2008 servers (13) decommissioning; planned 01/2020
-
[IS Apps] BEMS (2), Metering (5), Perspective Reporting (2) WS2008 servers upgrade; planned 01/2020
-
[IS Apps] Qlikview WS2008 server to be decommissioned; expected date now 02/2020
-
[CSE] ERI WS2008 servers (1) to be decommissioned; planned 03/2020
-
[IS Apps] Asta WS2008 Servers (4) to be upgraded; planned 05/2020
-
[IS Apps] Core HR servers (10) to be replaced by Core Systems ; 11/2020
-
[IS Apps] Class.net servers (4) to be upgraded; no date
-
[IS Apps] Kofax WS2008 server (1) to be replaced; no date
-
[IS Apps] O365 Provisioning WS2008 servers (2) to be upgraded, call in place; no date
-
[IS Apps] pCounter Application WS2008 servers (2); no date
-
[IS Apps] SQL Server 2008 WS2008 servers (4) to be decommissioned; databases still being migrated; end of support for SQL2008 was 07/2019
-
[ITI] CIS VOIP WS2008 servers (2) to be upgraded; no date
-
[Digital Library] Commander WS2008 server (1); no plan/date
-
[LST] Flexo WS2008 serves (1); no plan/date
-
[EUSA] WS2008 application servers (2); no plan/date
| Target Date | Title | Stage | Complete |
| 19-Dec-2017 | Profile servers build complete | Execute | Yes |
| 26-Jan-2018 | Detailed revision of DST, Print and EWS workstream plans | Plan | Yes |
| 13-Mar-2018 | Schools contacts informed of print server migration dates | Plan | Yes |
| 15-May-2018 | All owners of Schools based servers notified of Windows Server risks | Analyse | Yes |
| 15-May-2018 | All owners of Application servers notified of Windows Server risks | Analyse | Yes |
| 22-May-2018 | Test print server migrations completed and tested | Build | Yes |
| 28-May-2018 | Production print server pre-builds completed | Build | Yes |
| 24-Jul-2018 | All production print servers migrated or upgraded (excluding PDS cluster) | Deliver | Yes |
| 17-Sep-2018 | Legacy print test servers decommissioned | Deliver | Yes |
| 09-Oct-2018 | All legacy production print servers decommissioned | Deliver | Yes |
| 06-Feb-2019 | Start detailed planning for DST server workstream migrations and upgrades | Plan | Yes |
| 02-Jul-2019 | Migrate production PDS cluster (print servers) | Deliver | Yes |
| 03-Jul-2019 | DST licence servers upgraded | Deliver | Yes |
| 25-Jul-2019 | Windows 7 profile servers (Windows 10 dependency) upgraded from WS2008 to WS2016 | Deliver | Yes |
| 06-Jan-2019 | All ENT WS2008 servers migrated or upgraded to WS2016/2019 | Deliver | No |
| 14-Jan-2020 | Extent of exposure of unsupported WS2008 servers in Administration and Schools systems documented | Deliver | No |
| 14-Jan-2020 | End of Microsoft extended support for Windows Server 2008 | Deliver | No |
| 12-Feb-2020 | All DST WS2008 servers upgraded or decommissioned (dependency on DTP001 - Apps Ed) | Deliver | No |
| 04-Mar-2020 | Project closure | Close | No |
- Approved budget
- 510.0 days
- Activity this month
- 3.0 days
- Activity this year
- 29.5 days
- Activity to date
- 381.5 days
- Estimate to complete current year
- 38.0 days
- Estimate to complete future years
- 0.0 days