The purpose of this project is to prioritise and migrate the Windows 2003 and 2008 server estate to Windows Server 2016 to a supported level by the end of 2019. In addition, the project will monitor the estate in order to be ready to start planning the Windows Server 2012 to 2016 (or another Microsoft upgrade if available) in two years time.

Areas impacted include -

  • Roaming profile servers
  • Print servers
  • Desktop servers
  • Internal management servers (managed by ENT Windows Server team)
  • Schools servers (notification of risk only, upgrades subject to separate projects)
  • IS Application servers (notification of risk only, upgrades subject to separate projects)

Additional project documentation can be found at the project SharePoint site.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2020 BLUE 475.0 days 406.0 days 0.0

Project Info

Project
Windows Server 2016
Code
ENT023
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jan-2017
Planning Date
26-Jan-2018
Delivery Date
24-Feb-2020
Close Date
28-Feb-2020
Overall Priority
Normal
Category
Discretionary