Report for February 2020

Report Date
February 2020

Achievements in Last Period

  • 17 WS2008 servers upgraded or retired in the last month

  • DST Citrix/SCCM WS2008 servers (13) decommissioned/upgraded

  • Reduced cost 1-year MS extended security update (ESU) support for remaining WS2008 servers (36) being put in place
  • 319 WS2003/2008 servers from a total of 358 servers (89%) upgraded or retired during project
  • Project closure report drafted, reviewed, revised and approved

Risks/Issues

  • End of support date for WS2008 was 14/01/2020 with 36 servers still operational

Next steps

  • None

Transfer to ENT BAU

  • [IS Apps] Estates BEMS (2), Metering (5) WS2008 servers upgrades delayed to 02/2020
  • [IS Apps] Qlikview WS2008 (1) server to be decommissioned; expected date now 02/2020

  • [IS Apps] Kofax WS2008 server (1) to be replaced; planned 02/2020

  • [IS Apps] O365 Provisioning WS2008 servers (2) being migrated; decommissioning planned 02/2020

  • [CSE] ERI Inteum WS2008 servers (1) to be decommissioned; planned 03/2020

  • [ITI] DHCP WS2003 servers (3) to be replaced during CIS014; estimated 03/2020

  • [IS Apps] Asta WS2008 Servers (2) to be upgraded; planned 05/2020

  • [IS Apps] SQL Server 2008 WS2008 servers (4) to be decommissioned; estimated date 05/2020; end of support for SQL Server 2008 was 07/2019

  • [IS Apps] Core HR servers (10) to be replaced by Core Systems programme; estimated 09/2020

  • [IS Apps] Class.net servers (4) to be upgraded; no date

  • [EDINA] WS2008 Digimap servers (2) to be decommissioned; no planned date

  • [ITI] CIS VOIP WS2008 servers (2) to be upgraded; no date

 

Target Date Title Stage Complete
19-Dec-2017 Profile servers build complete Execute Yes
26-Jan-2018 Detailed revision of DST, Print and EWS workstream plans Plan Yes
13-Mar-2018 Schools contacts informed of print server migration dates Plan Yes
15-May-2018 All owners of Schools based servers notified of Windows Server risks Analyse Yes
15-May-2018 All owners of Application servers notified of Windows Server risks Analyse Yes
22-May-2018 Test print server migrations completed and tested Build Yes
28-May-2018 Production print server pre-builds completed Build Yes
24-Jul-2018 All production print servers migrated or upgraded (excluding PDS cluster) Deliver Yes
17-Sep-2018 Legacy print test servers decommissioned Deliver Yes
09-Oct-2018 All legacy production print servers decommissioned Deliver Yes
06-Feb-2019 Start detailed planning for DST server workstream migrations and upgrades Plan Yes
02-Jul-2019 Migrate production PDS cluster (print servers) Deliver Yes
03-Jul-2019 DST licence servers upgraded Deliver Yes
25-Jul-2019 Windows 7 profile servers (Windows 10 dependency) upgraded from WS2008 to WS2016 Deliver Yes
06-Jan-2019 All ENT WS2008 servers migrated or upgraded to WS2016/2019 Deliver Yes
14-Jan-2020 Extent of exposure of unsupported WS2008 servers in Administration and Schools systems documented Deliver Yes
14-Jan-2020 End of Microsoft extended support for Windows Server 2008 Deliver Yes
24-Feb-2020 All DST WS2008 servers upgraded or decommissioned (dependency on DTP001 - Apps Ed) Deliver Yes
28-Feb-2020 Project closure Close Yes
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
475.0 days
Activity this month
14.0 days
Activity this year
50.0 days
Activity to date
406.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Windows Server 2016
Code
ENT023
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jan-2017
Planning Date
26-Jan-2018
Delivery Date
24-Feb-2020
Close Date
28-Feb-2020
Overall Priority
Normal
Category
Discretionary

Documentation