Development technology resource confirmed according to the project plan
Missing Data - no update
Dynamat Modbus Pilot - no update
Optima Visualier - no update
Clarification was sought regarding the future direction of this project from the project sponsor and programme manager with regards to the options noted below. The initial feedback via the programme manager was to minimise the changes until the Energy Systems review is completed and so maintain the current plan, however, a meeting to review the strategy has been scheduled for 18th October
Maintain current project plan
import of missing data
upgrade to Dynamat Radio Bird
review of Dynamat cloud based solution
Review Dynamat cloud based solution and if proves to be fit for purpose
move to the cloud based solution
import of missing data would not be required
upgrade of Dynamat Radio Bird would not be required