Project journal

Title Description Author Post date
New Financial Journal Auto Upload Management System

The Journal Auto-upload Management System (JAMS) is now live.

JAMS address a long standing inefficiency with the management of financial transactions that originated outside of eFinancials.

The new JAMS functionality automates the interfacing of payment information from the WPM Card Payment site (ePay) into eFinancials removing the need for manual intervention and speeding up the journal posting process. Any problems with the payment data are automatically detected and the data owners alerted so that corrective measures can be taken.

Dawn Holmes 19-Sep-2013
Weekly update w/c 09/09/13
  • The installation of the live software went ahead as planned on Friday 6th Sept though the automatic overnight task wasn't activated until Monday 9th as a precaution
  • On Monday we liaised with WPM and Accommodation Services to activate the automation of delegate registration journal files
  • Files have been successfully loading into eFinancials and Accommodation Services have confirmed that journal data looks correct in eFinancials.
  • The Friday morning load encountered a problem downloading the daily file from the WPM gateway.  The cause is being investigated as a pre
Dawn Holmes 13-Sep-2013
Weekly update w/c 02/09/13
  • Live Implementation Plan completed and go-live booked for Friday 6th
Dawn Holmes 06-Sep-2013
Weekly update w/c 19/08/13
  • latest version of JAMS has been installed onto Test.  This version contains fixes to attach bad files to emails and to correct the sum errors for refunds.
  • delegate registration files seem to be posting correcting to test eFin
  • a training session has been book for FIS for w/c 2nd Sept to ensure that they know how to set-up and amend tasks
  • go-live is planned for w/c 2nd Sept
Dawn Holmes 23-Aug-2013
Weekly update w/c 05/08/13
  • The developer has been working on the 2 outstanding issues: attaching bad files to emails and sum errors for refunds.
  • The latest patches should be ready to go into Test next week and Dev resource has been lined up to install.
Dawn Holmes 12-Aug-2013
Weekly update w/c 29/07/13
  • Team meeting held to discuss options for Project Sponsor's request to access/modify invalid files.  Team recommendation is to attach a copy of the 'bad' file to the existing error notification.  The recipient will then be able to modify the file and manually load into eFin using Excelloader.  This provides a workaround for FIS and still complies with the Internal Audit recommendation.  An additional 5 days effort will be incurred and an anticipated delay of 2-3 weeks due to resource avaiilability and re-work.
  • Resource has been secured for the development of this additional requ
Dawn Holmes 02-Aug-2013
Weekly update w/c 22/07/13
  • JAMS re-work for delegate registration vat coding now in Test and awaiting suitable data from the WPM gateway so that Accommodation Services can sign off.
  • JAMS overview session given for FIS to broaden understanding of the application within the team
  • Project Sponsor raised a new requirement to be able to access and edit invalid files.  This had previously been specifically included on the recommendation of Internal Audit.
Dawn Holmes 02-Aug-2013
Weekly update w/c 15/07/13
  • Apps Manamgement have undertaken further testing this week
  • A number of minor issues have been identified which will be addressed when the developer returns from leave next week
Dawn Holmes 19-Jul-2013
Weekly update w/c 08/07/13
  • The revised software was re-installed into Test this week.  This revised version includes amendments for vat codeing for delegate registration, clearing of CLINK tables upon posting failure and some minor renaming in JAMS log files.
  • Integration testing is underway.
  • FIS have been notified that the system will be ready for UAT next week.
Dawn Holmes 12-Jul-2013
Weekly update w/c 24/06/13
  • The additional requirements identified by Accommodation Services (AS) late last week has meant that the live JAMS application cannot be activated.  Further discussions have taken place with AS to understand the details of the requirement and a revised has now been drawn up to include this change and redeploy later in July.  This change has impacted the project's timescales and budget but these increases have been agreed with Finance and the Programme Manager.  Additional information on the impact of this change can be seen in the issue/change
Dawn Holmes 28-Jun-2013
Weekly update w/c 17/06/13
  • Acceptance sign-off was achieved this week.  There were some provisos applied to the sign-off which have been documented in the acceptance milestone
  • The JAMS application is being implemented into Live but will remain inactive until the switchover process is confirmed with WPM (as this requires WPM to delete some old files manually posted files from their site to prevent duplicates).  We hope to activate the interface next Tuesday (25th)
  • A small amount of post-deployment work may be required to tidy up
Dawn Holmes 21-Jun-2013
Weekly update w/c 10/06/13
  • Test WPM files & manual csv files successfully loaded into eFin & posted
  • One remaining Jira with the developer for an enhancement to the description in eFin, this should be ready for testing by Monday
  • Draft plan drawn up to go-live mid-late next week.  These are tight timescales but we're keen to get the application live before our key contact in FIS leaves at the end of the month.
Dawn Holmes 14-Jun-2013
Weekly update w/c 03/06/13
  • Re-work has taken place for issues identified during user testing (Jiras)
  • Further user testing has taken place
Dawn Holmes 07-Jun-2013
Weekly update w/c 20/05/13
  • Awaiting resource from Dev Team to undertake UAT re-work but currently conflicting with project ITS102 which is overrunning on their deployment to Test.
Dawn Holmes 24-May-2013
Weekly update w/c 13/05/13
  • FIS are undertaking acceptance testing, this has thrown up a number of issues which have been logged in Jira.
  • Development resource is being sought for next week to address UAT feedback.

 

Dawn Holmes 20-May-2013
Weekly update w/c 06/05/13
  • Outstanding Jiras have been addressed and are back with Apps Management with re-testing
  • Resource secured for completing the deployment checklist in preparation for the go-live in June
  • FIS have started their acceptance testing
Dawn Holmes 10-May-2013
Weekly update w/c 22/04/13
  • The new application (JAMS) has now been integration tested by Apps Mgmnt with a small number of issues found.  The integration sign-off has subsequently been postponed to next week.
  • Meeting held with the tester and the developer to review the 6 outstanding issues: -
    • 3 are requests for enhancement which will be estimated and discussed with the business
    • 1 is a FIS request for more financial codes to be set up in Test
    • 2 are issues for the developer to resolve
Dawn Holmes 26-Apr-2013
Weekly update w/c 15/04/13
  • Meeting to handover from Dev Team to Apps Support
  • Integration testing started
Dawn Holmes 19-Apr-2013
Weekly update w/c 08/04/13
  • JAMS application was deployed to the Test environment ready for integration testing next week
Dawn Holmes 12-Apr-2013
Weekly update w/c 01/04/13
  • Due to the Easter break, no further progress has been made this week.
  • The final taks of repointing to new eFIn plus the deploy to Test are scheduled for next week (w/c 8th April)
Dawn Holmes 05-Apr-2013